$12.9B to meet rising power demand, advance CJIA expansion

Hinterland electrification and the expansion of the Cheddi Jagan International Airport (CJIA) will receive a share of the $12.9 billion in supplementary funding that the Committee of Supply approved Monday evening.

Minister of Public Utilities and Aviation Deodat Indar told the committee the allocation would help meet rising fuel costs and growing electricity demand and would cover construction payments for CJIA’s Terminal 2.

Minister of Public Utilities and Aviation Deodat Indar defends the allocation

Of the approximately $12.9 billion approved, $11.33 billion is allocated to electricity services, $1.56 billion to CJIA’s expanded work programme, and $52.44 million to accelerated hinterland electrification works.

“Right now, on every given night, the grid is seeing a demand between 250 and 260 MW. We don’t have that amount of generation. That is why you have these issues with outages because we are running neck and neck,” he explained.

Power generation has increased by 20 per cent compared with 2025. However, the expansion of communities, homes, businesses and infrastructure, along with the installation of approximately 70,000 streetlights in recent years, continues to drive demand.

Minister Deodat Indar, along with supporting technical staff

The electricity allocation includes $8 billion for Guyana Power and Light (GPL) Inc to support fuel purchases, with additional resources going to power entities serving Linden, Mabaruma, Mahdia, Port Kaituma, Moruca and Matthews Ridge.

In Linden, an additional $2.4 billion is being sought for fuel as peak demand has risen from approximately 14 megawatts to 16.9 megawatts.

“We made a commitment to get three more megawatts into Linden,” the utilities minister said, noting that a generator previously sent to the community was returned after encountering technical issues.

In the hinterland, the $52.44 million will fund two additional diesel generators with a combined capacity of 3.2 megawatts, helping to address a power generation shortfall in the coming months.

Meanwhile, the $1.56 billion for CJIA will help settle outstanding payments to the contractor constructing Terminal 2. The minister said the airport’s existing facilities had reached capacity amid growing passenger traffic.

“We had four airlines in 2020; now we have 16 flying this year. That increased traffic requires investment,” he said.

The new terminal is expected to cover approximately 180,000 square feet and is expected to be completed in early 2028.

Source link